DC06 Generator servicing and blackout test
Scheduled Maintenance Report for Juice Broadband
Completed
The scheduled maintenance has been completed.
Posted Nov 30, 2023 - 12:51 GMT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 30, 2023 - 08:01 GMT
Update
Date Change - *Black out test moved to same day as Generator servicing*
Posted Nov 23, 2023 - 15:36 GMT
Scheduled
*Black out test moved to same day as Generator servicing*
We would like to inform you that the data centre DC06 will be undertaking main generator servicing 30/11/2023.

There is no planned service impact, this is an advisory note, as there will be reduced resilience to services within and transiting the facility whilst the maintenance is being carried out.

In the unlikely event of a utility failure during the service and testing period, the load will be held by the UPS system as per normal and the generator brought back online.

Once the maintenance work is complete a blackout test will be performed to confirm all systems are operating as per specification.

Specialist Generator contractors will be on site to complete the scheduled maintenance, supervised throughout.

After servicing DC06 Datacenter will undergo a full load generator test.

This will involve simulation of a power failure to the site.

There will be no planned service impact, this is an advisory note, as there will be reduced resilience whilst the maintenance is being carried out. Power will remain unaffected to customer racks, but with reduced resiliency during the maintenance period. However, in the unlikely event of a utility failure during the testing period, the load will already be on the generators and would be returned to mains service at the earliest opportunity.
Posted Nov 30, 2023 - 08:00 GMT
This scheduled maintenance affected: Core IP Network.