DC06 Datacenter will undergo a full load generator test on the below date.
This will involve simulation of a power failure to the site.
There will be no planned service impact, this is an advisory note, as there will be reduced resilience whilst the maintenance is being carried out.
Power will remain unaffected to customer racks, but with reduced resiliency during the maintenance period.
In the unlikely event of a utility failure during the testing period, the load will already be on the generators and would be returned to mains service at the earliest opportunity.
Posted on
Jul 24, 2024 - 09:59 BST
CityFibre will be updating network infrastructure during this window. CityFibre connected customers impacted only.
CityFibre - "This is service affecting work; we expect services to remain available for the duration of the maintenance window except for a 5–10-minute window as upgraded cards are rebooted."