DC06 Blackout and generator test

Scheduled for Jan 27, 10:00 - 15:00 GMT

Scheduled

DC06 Datacenter will undergo a full load generator test on the below date.
This will involve simulation of a power failure to the site.
There will be no planned service impact, this is an advisory note, as there will be reduced resilience whilst the maintenance is being carried out.
Power will remain unaffected to customer racks, but with reduced resiliency during the maintenance period.
In the unlikely event of a utility failure during the testing period, the load will already be on generator power and would be returned to mains service at the earliest opportunity.
Posted Jan 21, 2026 - 14:00 GMT
This scheduled maintenance affects: Core IP Network.