Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 26, 2024 - 10:00 GMT
Scheduled
DC06 Datacenter will undergo a full load generator test on the below date. This will involve simulation of a power failure to the site. There will be no planned service impact, this is an advisory note, as there will be reduced resilience whilst the maintenance is being carried out. Power will remain unaffected to customer racks, but with reduced resiliency during the maintenance period. In the unlikely event of a utility failure during the testing period, the load will already be on the generators and would be returned to mains service at the earliest opportunity.