DC06 Datacenter will undergo a full load generator test on the below date.
This will involve simulation of a power failure to the site.
There will be no planned service impact, this is an advisory note, as there will be reduced resilience whilst the maintenance is being carried out.
Power will remain unaffected to customer racks, but with reduced resiliency during the maintenance period.
In the unlikely event of a utility failure during the testing period, the load will already be on generator power and would be returned to mains service at the earliest opportunity.
Posted on
Jan 21, 2026 - 14:00 GMT
The Riello UPS-A powering A-Feed to racks at DC06 in Poole is scheduled to have some preventative maintenance carried out.
During the works it will be required for the A-feed to be disconnected and / or bypass the UPS and be running from the mains, with the associated loss of UPS resilience for this feed. In the event of a power cut the A-feed will still be backed by generator but will lose power during the transition.
The B-Feed will remain backed-up by UPS-B and generator as usual, and as all racks are dual fed with 'A' and 'B' feeds no disruption is anticipated.
Posted on
Jan 21, 2026 - 16:46 GMT